Achievements
Achievements
Achievements
Three phase 14 of Tianjin Port Economic Zone, Cofferdam and Backfilling Project on Lifting Pipe
Customer:Tianjin Waterway Bureau Co., Ltd.
Work Barge:‘Junhao 3’ pipe laying barge
Location:Tianjin Port Economic Zone
Duration:Jun.10~15, 2012
BZ25-1 Oil Permanent Reproduction Project Old Subsea Pipe Crude Oil Replacement Engineering
Customer:Bohai Environmental Technology Services Company
Work Barge:"Junhao 3"
Location:Bohai Bay
Duration:Oct.9~Nov.27, 2011
COF1-6 Subsea Pipe Cleaning Engineering
Customer:Bohai Environmental Technology Services Company
Work Barge:"Junhao 3"
Location:Caofeidian 1-6 Oilfield area
Duration:Sep.2011
JZ9-3W Flexible Pipe Laying Engineering
Customer:Bohai Oil Harbor Engineering Co., Ltd.
Work Barge:Junhao 3
Location:Bohai Bay, CNOOC JZ9-3 Oilfield
Duration:Nov.~Dec. 2010
Boxinan Network Supply of LNG Deep Trenching Engineering
Customer:COOEC
Work Barge:Junhao 3
Location:Bohai Bay, Offshore areas
Duration:Jul.31~Sep.26, 2010
Pipe Jacking and Tunneling of Shanghai LNG Subsea Pipeline Engineering
Customer:Hyundai Heavy Industries Co., Ltd.(Korea)
Work Barge:Pull Equipment
Location:Nanhui District of Shanghai
Duration:Sep.~Dec, 2008
SZ36-1 1 Adjustment Project Spool Piece Installation Engineering
Customer:CNOOC
Work Barge:TIANWEI
Location:SZ36-1 Oil Field
Duration:Aug.6 ~Nov.18,2009
SZ36-1 1 Adjustment Project Protection Cage of Three-way Wye Installation Engineering
Customer:CNOOC
Work Barge:Junhao 3
Location:Liaodong Gulf, Liaoning Province
Duration:Sep.21~27, 2009
SZ36-1 1 Adjustment Project Newly Increase Subsea Pipeline Post Trenching ( hard clay)
Customer:CNOOC
Work Barge:TIANWEI
Location:BoHai Gulf, Liaoning Province, China
Duration:Jul.1 ~ Aug.5, 2009
SZ36-1 1 Adjustment Project Newly Increase Subsea Pipeline Post Trenching Engineering
Customer:CNOOC
Work Barge:Junhao 3
Location:Bohai Bay, China (Suizhong County, Liaoning Province)
Duration:Jun.21 ~Aug.18, 2009